Ireland and Ironwood intersection project moves onto Phase Five

City of South Bend

SOUTH BEND, Ind. -- The City of South Bend announced the Ireland Road and Ironwood Drive Intersection Improvement Project will move into Phase Five with construction shifting to the southeast corner of the intersection starting on or after Thursday.

During this phase, city officials say northbound traffic on Ironwood Drive won't be able to turn right onto Ireland Road.

A detour will direct traffic north on Ironwood Drive, east on Lincolnway East, then south on Church Street to reconnect with Ireland Road.

City of South Bend

Lane restrictions will remain in effect for traffic approaching from other directions.

Access to all businesses in the work zone areas will be maintained.

Phase Six of this project will be the final phase.

The improvement project includes a full reconstruction of the pavement, curb realignment and upgraded traffic signals.

City officials say each phase could take up to 21 days to complete, weather permitting.

The project is expected to be complete by early July, weather permitting.